Penn Lincoln Elementary School
Owner:   Altoona School District
    Altoona, PA
Contract:   HVAC
Contract Duration:   15 months
Completion Date:   October 1996
Contract Amount:   $733,500
Architect:   Hayes Large Architects
Altoona, PA
     
 
The HVAC renovation and addition contract included removing the existing steam system and installing a new two-pipe hot water and chilled water system while the building was occupied. American Air Filter unit ventilators, McQuay chiller, H.B. Smith boilers and a DDC Controls System by Landis and Staefa were some of the key equipment installed on this project.
     