Concurent Technologies Corporation (CTC)
Industrial Park - ETF Building
Owner:   CTC
    Johnstown, PA
Contract:   Plumbing and HVAC
Contract Duration:   12 months
Completion Date:   September 1992
Contract Amount:   $1,327,000
Architect:   Oswald Associates
Huntingdon, PA
     
This renovation project included the installation of Temtrol roof top units with hot water and chilled water coils, along with Dunham Bush chillers and Bryan gas fired boilers. Our contract included piping distribution throughout the plant for future processes that required domestic cold and hot water, natural gas, compressed air and chilled water supply and return.
 
Base mounted "Bell & Gossett" hot water pumps serving ETF Building at CTC.
 
Three "Bryan" gas fired hot water boilers installed at the ETF Building. One 2,100,000 BTU, one 1,500,000 BTU and one 900,000 BTU.
 
180-ton Dunham-Bush rotary screw chillers.
 
     
Previous Job Next Job


 
Copyright © 2003 Mervac Plumbing & Heating, Inc.
135 5th Street ~ Suite 2 ~ Windber, PA  15963

Contact us at mervac@pennswoods.net